Energy Efficiency: the importance of site supervision

On our Facebook page, we are regularly publishing images from our Cavriago construction site, where we are building two Passive Houses.

With this article, we would like to show just two examples of the many construction errors that can occur during the scope of the works, even working with an accurate contractor, proving that careful site supervision is necessary to meet a high level of quality and efficiency.

The detail we are going to write about is the perimeter of the foundation of the thermal envelope. The foundation itself is a concrete slab sitting on top of a drainage layer made of cellular glass gravel. On the sides, the slab is insulated with a panel of cellular glass.

perimeter insulation - Emu Architetti
Detail photo: the concrete slab sits on top of the cellular glass gravel (on the left), with a panel of cellular glass as perimeter insulation.
The detail as designed. Arrow pointing to continuous insulation.
The detail as designed.
Heat flow through the detail as designed.
Heat flow through the detail as designed.
Isotherms along the detail as designed.
Isotherms along the detail as designed.

No matter what calculations or drawings are made during the design phase, such a delicate detail of the thermal envelope cannot be left to be executed without supervision.

In the case of our site in Cavriago, the work was executed very well, with a separation layer of polypropylene geotextile between the glass gravel and the concrete (see the white strip in the picture below).

before the perimeter insulation panel was installed
The detail as perfectly executed, before the perimeter insulation panel was installed.

PROBLEM #1: CONCRETE LEAKS

In some isolated spots, the concrete leaked out from underneath the formwork panel, as you can see in the image below.

Concrete leaked out from underneath the formwork
Concrete leaked out from underneath the formwork, and mixed with the glass gravel.

This is no doubt a thermal bridge. Is it a bad one? It depends. If you are building a Passive House, these details matter a lot.

We calculated the effect of this thermal bridge, using a finite element software:

Detail showing the concrete leak.
Detail showing the concrete leak.
Heat flow: notice the concentration through the concrete leak.
Heat flow: notice the concentration through the concrete leak.
Isotherms change because of the construction mistake.
Isotherms change because of the construction mistake.

According to our calculation, the concrete leak as shown would increase the heat flow through the detail by approximately 4,2%. Calculating the sum of the (few) leaks along the perimeter, it would bring an increase in net energy demand of the whole building of a full 1%. Is this a lot? For a passive building, it is.

When considering comfort, on the other hand, if this error is a few isolated spots (not continuous), it does not have a real effect on the indoor temperature.

PROBLEM #2: HOLES TO FIT REBARS

Another risk for unexpected thermal bridges is given by the holes made through the vertical insulation panels to allow rebars to connect the (warm) foundation concrete slab of the house to the adjacent one of the garage (not yet cast at the time the photos were taken).

The hole cut through the panel is about 30 mm high: if we sum up the individual lengths of these cuts along the perimeter of the foundation, the total amount reaches 7,20 m.

The rebars go through the vertical insulation panels.
The rebars go through the vertical insulation panels.

Again, we calculated how bad it would have been if we had left this detail to the business as usual (BAU) practice to fill this void with standard concrete.

BAU detail, with the cut filled with concrete.
BAU detail, with the cut filled with concrete.
BAU heat flow.
BAU heat flow.
BAU isotherms.
BAU isotherms.

If not avoided, this BAU construction mistake would have increased the heat flow through the node by 4,6%, with an increase in the net energy demand of the whole building of 1,6%.

CONCLUSIONS

The higher the goal, the better the execution needs to be. This relies first on high quality design, and then on attentive site supervision.

In one single day of works, we risked making the whole building envelope 2,6% worse than designed. And we are just at the foundations of the building.

This is not necessarily the contractor’s fault: building is difficult. Among Client, Architects and Contractor there needs to be an understanding to maximize teamwork and communication. Whoever is in charge of site supervision needs to be present, and aware that these kinds of problems can happen and do matter.

On the bank on the right: the clumps of concrete mixed with glass gravel, once removed from the perimeter.
On the bank on the right: the clumps of concrete mixed with glass gravel, once removed from the perimeter.
waterproof foam
The lower row of cuts have been filled with waterproof foam before casting the concrete. The top ones are going to be filled in the same way as well..

5 comments

Leave a Reply

This site uses Akismet to reduce spam. Learn how your comment data is processed.

Discover more from Emu Passive

Subscribe now to keep reading and get access to the full archive.

Continue reading